Tighten it the same way you would if you were stacking it.  From the bottom up. 
 
It will be hard to straighten it if you tighten the top guys and then have to 
straighten out a bend in it at the lower guys.
I have always used pier pins and they require the guys to get it plumb and hold 
it up as you stack it.
Earl
N8SS
Message: 8
Date: Tue, 19 Nov 2013 08:03:57 -0800 (PST)
From: Rex Turvin <turvin2009@yahoo.com>
To: towertalk <towertalk@contesting.com>
Subject: [TowerTalk] guy wire ?
Message-ID:
        <1384877037.18169.YahooMailNeo@web126101.mail.ne1.yahoo.com>
Content-Type: text/plain; charset=iso-8859-1
I am going to use a crane to lift a 60' Rohn 25 tower. I am using 2 sets 
of guy wires. 1 set at 28' and the other at 55' per Rohn.
The guy wires will be attached to the tower when lifted. My question is 
this: which set should? be tightened 1st? Top set or bottom set? Or does 
it matter?
73 NR6M
?
ex: KF7NMD
Sincerely,
Rex Turvin
www.nr6m.com
_______________________________________________
_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk
 |