I recently installed a 30' Universal tower. Before pouring the concrete 
into the appropriately sized hole, I added several inches of crushed rock 
to the bottom of the hole for drainage of the base legs. Sometime after 
pouring the concrete, I noticed that two of the three bases legs (which are 
largely embedded in the concrete) were not draining. I could see water in 
the legs nearly up to the top, just below where the hinged base attaches to 
the bottom tower section..

I'm assuming that in pouring the concrete, the contractor and I somehow 
managed to get some of it under the legs, even with the several inches of 
drainage rock, thus preventing adequate water drainage.

My question is whether anyone has a feeling of how serious a problem this 
lack of water drainage is. Will this prolonged exposure of the steel legs 
to water likely cause any structural integrity problems?

Richard Eckman  KO4MR
Hampton, VA
ko4mr@arrl.net


--
FAQ on WWW:               http://www.contesting.com/towertalkfaq.html
Submissions:              towertalk@contesting.com
Administrative requests:  towertalk-REQUEST@contesting.com
Problems:                 owner-towertalk@contesting.com
Search:                   http://www.contesting.com/km9p/search.htm


<Prev in Thread] Current Thread [Next in Thread>