- 1. [TowerTalk] Using a crane to lift partially assembled towersections... (score: 1)
- Author: CCTPAUL@aol.com
- Date: Wed, 17 Mar 2004 13:15:51 EST
- Hello All, Looking for comments / suggestions on the following tower project: The plan is to install a guyed 70 foot Rohn 25G tower this summer. I'm fortunate to have a good friend who has a crane wh
- /archives//html/Towertalk/2004-03/msg00288.html (9,045 bytes)
- 2. Re: [TowerTalk] Using a crane to lift partially assembled towersections... (score: 1)
- Author: GALE STEWARD <k3nd@yahoo.com>
- Date: Wed, 17 Mar 2004 10:52:46 -0800 (PST)
- Hi Paul, A couple of thoughts: Two people can "walk up" 30 ft of R25. My wife and I did it when I installed my tower. Since you have a convenant "pull point", it may be easier just pull it up with a
- /archives//html/Towertalk/2004-03/msg00289.html (8,215 bytes)