At 05:44 AM 3/18/2004, FireBrick wrote:
I'm a retired Chicago Licensed Mason Contractor.
It MUST be a unified pour.

Believe it or not, it's very hard to get concrete to stick to previously poured concrete.
Except of course, where you don't want it to. :-)



----- Original Message ----- From: "Brian Lambert" <n1ik@n1ik.com> To: <towertalk@contesting.com> Sent: Wednesday, March 17, 2004 9:30 PM Subject: [TowerTalk] Question on concrete pour for self-supporting tower...


> Hi, > > Could anyone tell me whether one must pour all the concrete for a > self-supporting tower base in one pour, or is it OK to mix up bags of > concrete over n weekends, and pour them into the form as you go? > > Reason I ask is that it might be hard to get a concrete truck to where I > need it to go, so I'm thinking about alternatives. > > 73 de N1IK, Brian > _______________________________________________ >

you can have it pumped in butt the rent and operator mite cost the same as the concrete kb9yku


_______________________________________________


See: http://www.mscomputer.com for "Self Supporting Towers", "Wireless Weather Stations", and lot's more. Call Toll Free, 1-800-333-9041 with any questions and ask for Sherman, W2FLA.

_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>