I figure if the engineer said"5 by 5 by 9" I'd make it "5 by 5 by 9" and not 
worry about it.Yes it may cost a little more but when you're spending 
several G's on it does 100-500 dollars one way or the other REALLY matter.
    The simple fact is they designed it with a square hole,which are NOT 
hard to dig out.No pro should have a hard time with a 5 by 5 by 9 hole.It is 
plenty wide to get the bucket in there and dig it out.I rented a mini and 
dug two holes 3.5 by 3.5 by 5 and I was done in 3 hours and it was FUN.I was 
able to get it square enough for my tastes,plus if your in an area that gets 
frost you don't want the cement to hang over the undug part.The frost will 
work it out of the ground OR break the cement off at the junction.Just the 
way it is,don't ask how I know thet either hi hi hi.  Gregg  K9KL 


_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>