Gary McConville wrote:
> Roger,
> Unless the math has changed, it looks like you'll need
> 72 sq ft or 8 cubic yards.

Geez, I certainly hope not. Actually, the total square feet of a
4X4X5' hole is 80 cubic
feet.

But a cubic yard has 27 cubic feet of concrete in it. And 80/27=2.96
cubic yards.

If you can't pay for a pumper, then you're left with 2 choices. Dig
another hole, or cart it back there and do it the hard way.

):>
Ed