[TowerTalk] Tower Base and rebar

Dfmich@aol.com Dfmich@aol.com
Thu, 1 Oct 1998 22:40:14 EDT


Two questions for the assembled multitude

1. The drawing for my tower base shows the rebar cage stopping 3 in short of
the bottom of the concrete block. Any thoughts on how to provide this spacing.
I am wondering how I keep the rebar assembly in place whilst the concrete is
poured around it if the rebar doesn't sit on and get attached to the bottom of
the hole somehow.

2. I have read that you should not pour concrete from a height greater than
about 4 ft. The hole for my base is 6 ft deep so how do I address this
dilemma. I have read also that one solution is to have the concrete placed
using a pump. How does this work.

Thanks in advance for your thoughts
Dan K9EA

--
FAQ on WWW:               http://www.contesting.com/towertalkfaq.html
Submissions:              towertalk@contesting.com
Administrative requests:  towertalk-REQUEST@contesting.com
Problems:                 owner-towertalk@contesting.com
Search:                   http://www.contesting.com/km9p/search.htm