[TowerTalk] Rohn 25 vs 45 ?
K7LXC@aol.com
K7LXC@aol.com
Tue, 6 Apr 1999 20:23:14 EDT
In a message dated 99-04-06 01:31:10 EDT, km1h@juno.com writes:
> One procedure that I do use that I rarely see mentioned is the use of a
> transit for erection. I'll spend that extra hour or two getting
> everything absolutely vertical and as close to equal guy tension as I
> can.
Unfortunately a transit requires a moderate learning curve and money
for rental. TIA-222 specs say that you can be out three inches in 100 feet
and you can eyeball it that close. While I've used a bubble level many times,
if you can get ahold of an electronic level (good to a tenth of a degree!) or
a level for dish installations (1/4 degrees) - use it to plumb the bottom
section. Then you can sight up the face and plumb the rest of the tower
visually; it'll be pretty darned close. Or use the aforementioned levels to
plumb each set of guys. Either way is good enough for me.
Cheers, Steve K7LXC
Tower Tech
--
FAQ on WWW: http://www.contesting.com/towertalkfaq.html
Submissions: towertalk@contesting.com
Administrative requests: towertalk-REQUEST@contesting.com
Problems: owner-towertalk@contesting.com
Search: http://www.contesting.com/km9p/search.htm