[TowerTalk] Pad and Pier Foundations

Kelly Johnson n6kj.kelly at gmail.com
Mon Jul 11 16:26:17 EDT 2005


Yes, they probably use a back hoe.  I suspect the answer to my
original question about how they build the pad-and-pier holes is that
they dig the hole big enough for the pad, insert a form for the pier,
pour the pad and pier, wait for them to dry, then backfill.  My
original question really was: is backfilling OK for these types of
foundations?  All foundations I had seen in the past required
"undisturbed soil" around the foundation.  I couldn't see how this
could be accomplished for this type of foundation.  I guess
backfilling for this type of foundation is not only OK, but probably
the only practical way of doing it.



On 7/11/05, Alan NV8A (ex. AB2OS) <nv8a at att.net> wrote:
> Back hoe?
> 
> 73
> 
> Alan NV8A
> 
> 
> 
> On 07/11/05 03:25 pm Kelly Johnson tossed the following ingredients into
> the ever-growing pot of cybersoup:
> 
> > OK, I can buy that.  So, if they are spec'ing square holes for
> > commercial users then those commercial users must have a reasonable
> > way of creating the required holes.  It seems unlikely to me that they
> > go down to Home Depot and hire a couple guys from the street to dig
> > the hole by hand :-)  Anyone know what the commercial guys do?
>


More information about the TowerTalk mailing list