[TowerTalk] New tower install

Merlin-7 KI4ILB merlin-7 at sc.rr.com
Tue Aug 15 18:28:14 EDT 2006


Some time in the next year I plan on installing a new tower in North Carolina. It will most likely be 100' or less out of rhon 25 g.

 I was planning on making the base much like the one I have now.

 It has 3 galvanized pipes installed into the slab that the rhon 25g slides into.

 I have a few questions....

 Would it be better to buy the short base sections and pour the concrete around them? I know they were made for this but I worry about the thin wall of the rhon corroding over time due to the contact with the wet/damp concrete.

 Next question.....

 After the hole is dug, the rebar installed and either the short tower section or galvanized pipes are in place, how would you install the ground rods?

 The tower will be right next to my shack so I was planning to place the rf/lightning ground common point there.

 I could place 1 or more ground rods in the hole before the concrete is poured and radiate out from there. It would be a lot simpler to add all my ground connections under the tower before the concrete is poured.

 Would you make the common point under the tower or beside it where it could be accessed later?
 Or maybe even have the center ground rod sticking out of the slab near the middle of the tower and connect the others to that point?

 Thanks 
 Joe KI4ILB

 It never hurts to plan ahead...


More information about the TowerTalk mailing list