[TowerTalk] CONCRETE CURING

Mike, K6BR noddy1211 at sbcglobal.net
Mon Aug 28 19:41:52 EDT 2006


I would say one week is not enough, remember the compression/tension from a
tower in wind is a lot more stressful than foundations.  I think you are
guessing, the people who poured my concrete said they always recommend 3 to
4 weeks for towers or longer for complete curing.

Mike


Most builders will cap a foundation within a week of a pour.

Lots of them  will start framing at the same time. My sense is a week 
is good enough.





73, Craig Clark, K1QX