On 5/5/13 11:29 AM, EZ Rhino wrote:
> Jim Sez:
>
> Bond your copper grounding wire (which comes into the concrete
> through the top)to the rebar cage. or run 20 feet of the copper wire
> around through the concrete, as long as it's totally encased.
>
> I ask: What difference does doing the above make when the tower
> itself is already set in the concrete, whether it be literally in the
> concrete (like setting the first section of 25g in the hole) or the
> anchor bolts set 3' into concrete for a crank up tower?
>
IN that case, no difference..
Sometimes, though, you want a separate wire (maybe it's easier to hook
to a panel that has coax connectors on it)