yes. all of my towers have at least part of a tower section, some have a whole tower section, above the top guy wires... then of course there is a mast above that.
when tramming the top 40m yagi on my 180' tower the tram wire is about 8' above the top guys, I do run a back stay the opposite direction to keep the stress off the tower joint.
Mar 24, 2014 03:03:59 PM, infomet at embarqmail.com wrote:
Is it common to work above the top guys, after installation?
I’m not sure I’d want to handle a heavy beam or do tramming above a joint.
I “think” it would be OK, but would like to hear from TWHDI (those who have done it).
WL