[TowerTalk] Concrete Pad for U.S. Tower TX-472
Chris Wynn
n4xfa at yahoo.com
Fri Jul 24 23:25:10 EDT 2015
I am in the process of putting up a TX-472. So far, I have been relatively lucky and things have gone pretty smoothly. I dug the hole using an excavator and "slightly" over dug it by a few feet. From my initial calculations, I should have needed just under 8 cubic yards, but ended up pouring 16 cubic yards (32 tons and $2k more)!
So far the concrete has sat for 7 days curing in the Georgia sun. I have been pretty cautious to keep water on it, and covered pretty well.
I know that the specs call for that concrete to cure for 28 days. However, how early can I raise this tower? Does anyone have any experience with cheating the 28 day curing period? I was kind of hoping to raise it at the 21 day point.
I guess the last real job is to trench from the tower back to the shack. Therefore, I plan on spending the next couple of weeks burying hardline.....
Thanks y'all and see you in the pile ups!
73's es CUL,
ChrisN4XFA
Christopher L. Wynn
Attorney-at-Law
Christopher L. Wynn, ESQ., P.C.
6716 Church Street, Suite B
Douglasville, Ga., 30134
(770)942-8661 (Landline)
(770)577-1626
chris at chriswynnlaw.com
More information about the TowerTalk
mailing list