[TowerTalk] My first tower section is not plumb...

Steve Maki lists at oakcom.org
Fri Feb 12 08:12:48 EST 2016


I've used that method myself on towers that had suffered vehicular 
damage near the base, works well.

In fact another option for Doug, if he's going to be forming up a new 
block of concrete above grade, would be to take this opportunity to 
convert to some version of a pier pin install.

-Steve K8LX

On 2/12/2016 12:11 AM, Stan Stockton wrote:

> Doug,
>
> If that tower is actually so out of plumb that you have to fix it,
> this is what I would do:
>
> 1.  Bend the legs just enough, within an inch of the bottom, that you
> can push the tower with significant force by one person BY HAND from
> ground level so it is straight.  Paint the bottom 16 inches of the
> tower and also coat it with some roofing tar, at least where you
> hammered.
>
> 2.  Drill four, six inch deep holes in the existing concrete in a
> square outside the area taken up by the tower.  Install and epoxy, if
> you have the proper epoxy, rebar in those holes extending up about 15
> inches.
>
> 3. Make a form around your existing base about 12 inches larger both
> length and width than your existing pad X 16 inches tall.  If the
> existing pad is 24" X 24", make the form 36" X 36".  Install rebar in
> the new form above the existing concrete pad and down into the new
> pour area.
>
> 4.  Pour the new concrete using three plumb bobs (one on each leg)
> and with tower perfectly plumb (check it with a good level on all
> three legs in the direction where the guy wires will go to the
> anchors) and let it cure for however long you want - 14 days should
> be good.
>
> In my opinion there is a lot more potential for creating worse
> problems than what you currently have in trying to move a 2000 pound
> block of concrete buried 3 feet in the hard ground with 20 feet of
> R25G sticking out of it.  You certainly don't want to put extreme
> force on one leg of the tower at 15 or 20 feet with a guy wire in an
> effort to move the concrete.
>
> Remember that the only purpose of a tower base on a guyed tower is to
> keep it from sinking in the ground.  Originally you were going to
> have it sit on top of a plate on your roof.  Oh, yes, this is
> overboard, but probably less work than trying to move the concrete.
>
> Use good, temporary guy wires with proper tension and put up the last
> section or two and antenna in a safe manner.
>
> 73... Stan, K5GO
>
>> On Feb 11, 2016, at 5:51 PM, Douglas Ruz (CO8DM)
>> <co8dm at frcuba.co.cu> wrote:
>>
>> Hi,
>>
>> I have been thinking and I am really want my tower straight and
>> plumb.
>>
>> I am considering digging out some side of the base to adjust the
>> tower level.
>>
>> Any tips or thoughts ???
>>
>> Can I just digging 2 sides or all 4 sides of tower bease???
>>
>> About backfilling...what is the best add concrete again for
>> backfilling???
>>
>> what is the best method to move the base to adjust the level
>> ??...it is about 2000 pounds base.
>>
>> Thanks in advance,
>>
>> 73....Douglas, CO8DM
>>
>> "No creo que haya alguna emoción más intensa para un inventor que
>> ver alguna de sus creaciones funcionando. Esa emoción hace que uno
>> se olvide de comer, de dormir, de todo." - Nikola Tesla -----
>> Original Message ----- From: "Steve Maki" <lists at oakcom.org> To:
>> <towertalk at contesting.com> Sent: Wednesday, February 10, 2016 8:26
>> PM Subject: Re: [TowerTalk] My first tower section is not plumb...
>>
>>
>>> If your tower is the equivalent of R25, and only 30', there's not
>>> much you can do to it to really overstress it, unless you try
>>> real hard.
>>>
>>> But if you really want it straight AND plumb, consider digging
>>> out the appropriate side of the foundation and letting the the
>>> concrete adjust itself, and then backfilling it back in.
>>>
>>> At that point it will become what you want it to be, merely an
>>> anti-sink device.
>>>
>>> -Steve K8LX
>>>
>>>> On 2/10/2016 8:08 PM, Douglas Ruz (CO8DM) wrote: Thanks for all
>>>> replys.
>>>>
>>>> OK, first, I will build a Gin Pole...I think it is not a
>>>> problem.
>>>>
>>>> Second, seems that my verticality errors are "into" the
>>>> tolerance range, so, I think I can do some corrections before
>>>> tighten the bolts...I put some pressure in one of the temporary
>>>> guys and make the 2nd section plumb. In general the tower (only
>>>> 2 sections now) is very stiff with "My temporary guy ropes"...I
>>>> climb to the top of the 20ft to attach the line with weight
>>>> (plumb bob) in the center of the tower and I dont feel any
>>>> movement.
>>>>
>>>> My questions is:
>>>>
>>>> Can I try to make the tower plumb without adding to much stress
>>>> to tower legs???