Great job on completing the base.
Sorry - but on the word of caution, none of us know how the concrete was poured or mixed.
With this in mind, a 30 day wait is best.
James
--------------------------------------------
On Mon, 1/11/16, DALE LONG <dale.long at prodigy.net> wrote:
Subject: Re: [TowerTalk] Rohn 25G clone born few minutes ago...
To: "sawyered at earthlink.net" <sawyered at earthlink.net>, "towertalk at contesting.com" <towertalk at contesting.com>
Date: Monday, January 11, 2016, 11:08 PM
For most purposes 7-10 days should be enough to begin building a tower. No need to wait one month unless you are building a monster
tower.
Dale - N3BNA
From: Ed Sawyer <sawyered at earthlink.net>
To: towertalk at contesting.com
Sent: Monday, January 11, 2016 11:12 PM
Subject: Re: [TowerTalk] Rohn 25G clone born
few minutes ago...
Congrats Douglas!
The Concrete manuals say that concrete will reach 75% of its 28 day rated strength in 7 days. Almost 90% in 14 days. For tower building, 14 days is
already overkill. 7 days is plenty. Obviously, the other question is what was the specified mix strength. If you have 5000PSI concrete, then its
already stronger than typical building foundation concrete after only 7 days of cure.
Ed N1UR