[TowerTalk] Lifting a pre-built section of tower using a crane - how to strap it off

Fred Keen fredkeen at ymail.com
Wed Oct 12 11:19:45 EDT 2016


As you lift the tower, it was a lot easier for us having three men to hold the guy wires away from the tower as it was lifted.
Have you given any thought to how you're going to move the bottom of tower as the crane lifts it? We used a small front end loader bucket, there is not a lot of weight involved but the bottom will drag the ground until the point where the crane has the tower section off the ground.
Fred  KC5YN 

    On Wednesday, October 12, 2016 9:19 AM, R Morris <robrk at nidhog.net> wrote:
 

 The crane guy will know how, and usually pick up at the 60% point. In your case, 40 feet, and a choker around the whole tower. 

Sent from my iPhone

On Oct 12, 2016, at 10:06, StellarCAT <rxdesign at ssvecnet.com> wrote:

Ok,

Another question: so I have this 60’ long section of R55 with a rotating ring at the 48’ point which will have guys hanging down from it ... the weight is probably around 850#. The tower is laying with the top closest to where the crane will be set up (probably 50’ away from its nearest end) and the tower going away from the crane. 

How do I ‘strap’ this for the crane to lift it? 

I’m concerned that the rungs are not strong enough – their welds – to strap around them ... do I somehow wrap around the legs using three straps all going up to the hook? 

Gary 
K9RX

_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk at contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk at contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk


   


More information about the TowerTalk mailing list