[TowerTalk] Concrete base - tower
Steve Maki
lists at oakcom.org
Fri Oct 13 09:02:35 EDT 2017
Sure, because they are trying to minimize concrete. A huge block of
concrete always works, the same as a big tower works in place of a
little tower. I'm trying to envision a situation where replacing dirt
with concrete causes an issue....
That said, it's not THAT hard to do a pad & pier. You have to be ready
when the concrete comes, same as always.
-Steve K8LX
On 10/13/2017 8:47 AM, Dick's wrote:
> Even if you are not getting a permit, changing the foundation is asking, in my opinion, for problems. I have seen the design engineer's calculations for the foundation and it is pages of heavy duty stress/strain formulaes.
>
> Regards,
> Dick, K0CAT
More information about the TowerTalk
mailing list