[TowerTalk] Looking for some foundation advice

Jeff Blaine KeepWalking188 at ac0c.com
Thu May 28 01:50:25 EDT 2020


I don't think the water is an issue for the foundation, but I can say 
from personal experience it sure can be a headache with respect to 
INSPECTION if that's needed prior to the pour.

Inspection was required at my site and the inspectors wanted to see no 
more than 1/2 inch of standing water.   And the rebar had to be in 
position when the guy came to inspect which was another headache.  I 
could not drop the cages into the holes because repeated rains would 
cause slight sidewall erosion and the nice initially square holes would 
round-out taking on a bowl shape. Hired two high school guys to square 
out the holes when it looked like things were drying up a bit, of course 
each time the hole got a bit bigger.

There were 12 holes we wanted to pour and it took 3 months of waiting to 
find a time window where most of the holes were dry.  I think there were 
3 of them that had to be pumped and one was at a point in the yard where 
it would fill up in a couple of hours. For that one I sunk a 5-gallon 
bucket into the bottom of the hole so the top was flush with the hole 
floor.  That would let the sump pump fit down through the rebar and into 
the bucket where it would keep the hole drained.  I ran the generator 
and pump until the inspector showed up.  Pulled the pump.  He looked at 
the hole and signed it off.

Poured the 12 holes all in one day.  Each guy anchor ended up taking 
about a yard more concrete than Rohn spec - that increase from all the 
sidewall cleanup by the boys over the summer.  For sure those things are 
never going to fly out of the ground, no matter how big the tornado is 
that comes calling...

If the county would have let me poor the holes with water in them, I 
could have had the project done months earlier!

So my guess is that the water is not a issue with respect to the tower 
base, but it is going to provide some challenges in other areas.  Good luck!

73/jeff/ac0c

alpha-charlie-zero-charlie
www.ac0c.com


On 5/28/20 12:36 AM, Mickey Baker wrote:
> Hi Don, and all,
>
> I live in Florida and once had a bridge and connecting seawall adjacent to
> my property replaced.The new seawall connected to mine, so I watched the
> pour right next to my dock with interest.
>
> They brought in an excavator, dropped sheet steep forms on the water side
> of the new seawall and used the excavator and removed the old seawall and
> several yards of muck. Water never drained - they built a plywood form into
> the water on the land side of the seawall and steel sheets on the water
> side, all the way up to a piling on the bridge. A long steel rebar cage
> with a coating (zinc chromate? Yellow) was placed into the trough.
>
> The pour was supervised directly by the project engineer. He examined
> everly load with a slurry test and the chute from 3 trucks full of
> readymix was poured into a placement box, a 12" plywood square tube about
> 6' long reinforced with steel straps every foot or so. It fit perfectly
> between the rebar. A worker stood on the form and filled the tube so that
> it placed the concrete into the bottom of the pour without mixing with sea
> water and picked it up and moved down the rebar squares, got to the end and
> started back. There were four courses, so it appears they placed 2 feet per
> vertical course. The final course was above water and was poured directly
> and finished.
>
> So concrete is placed directly into water - into sea water even - and lasts
> for decades.
>
> As everyone has said, find yourself a good engineer who knows how to design
> and pour footings in your local geology. It will be good money spent!
>
> Mickey Baker, N4MB
> Palm Beach Gardens, FL
> *“The servant-leader is servant first… It begins with the natural feeling
> that one wants to serve, to serve first. Then conscious choice brings one
> to aspire to lead." Robert K. Greenleaf*
>
>
> On Wed, May 27, 2020 at 6:44 PM Don Solberg <dsolberg8132 at gmail.com> wrote:
>
>> I was planning on purchasing a used US Tower HDX-572, 72 ft crank up
>> tower.  It looks like I may have run into a problem with the foundation.  I
>> had some trenching done today for a new well and discovered that the ground
>> water level is just slightly lower than 6ft.  US Tower specifications call
>> from a 7.5 foot deep hole. My soil is mostly sand, so in addition to not
>> being able to go down 7.5 ft, I probably also want to make the foundation
>> wider.
>>
>> Is it practical to put up the 72ft tower with a wider pad, or should I look
>> at getting a smaller 55ft tower?  Another alternative is find another
>> location for the tower.  I have about a 10 ft hill on another property that
>> I own across a gravel road.  This would most likely eliminate the ground
>> water problem but I would have about a 300 ft cable run and I would have to
>> trench across the town's gravel road.
>>
>> I am looking for recommendations.
>>
>> 73,
>>
>> Don K9AQ
>> _______________________________________________
>>
>>
>>
>> _______________________________________________
>> TowerTalk mailing list
>> TowerTalk at contesting.com
>> http://lists.contesting.com/mailman/listinfo/towertalk
>>
> _______________________________________________
>
>
>
> _______________________________________________
> TowerTalk mailing list
> TowerTalk at contesting.com
> http://lists.contesting.com/mailman/listinfo/towertalk


More information about the TowerTalk mailing list