I just poured a base for a self-supporting US Towers TX-455 - the local
concrete guys said 7 days is sufficient. I used 4000 psi concrete, and the
daily highs were in the 50s, lows sometimes into the low teens. I'd check
with the local concrete company - they know their product, local weather
conditions and the specifications. http://home.centurytel.net/WD0M/ Click on "Tower Project". This is a semi-unique installation - I couldn't dig a hole for the concrete because it is solid bedrock on nearly all the five acres. The decision was to drill holes in the rock, cement re-bar in place, and pour a concrete block around the rebar cage. It worked out fine. 73, Joe WD0M At 08:56 AM 12/5/2003, Alan Beagley AB2OS wrote: I am sure I read a recommendation to wait at least a *month* on one of the tower manufacturers' Web sites. _______________________________________________ See: http://www.mscomputer.com for "Self Supporting Towers", "Wireless Weather Stations", and lot's more. Call Toll Free, 1-800-333-9041 with any questions and ask for Sherman, W2FLA. _______________________________________________ TowerTalk mailing list TowerTalk@contesting.com http://lists.contesting.com/mailman/listinfo/towertalk |
Previous by Date: | [TowerTalk] 75 and 160 m antenna, R. Earle Sanders |
---|---|
Next by Date: | Re: [TowerTalk] RE: Erecting tower, Tom Anderson |
Previous by Thread: | Re: [TowerTalk] RE: Erecting tower, Alan Beagley AB2OS |
Next by Thread: | Re: [TowerTalk] RE: Erecting tower, gdaught6 |
Indexes: | [Date] [Thread] [Top] [All Lists] |