Re: [TowerTalk] Tower Base Concrete Cure Time

To: Jim Brown <jim@audiosystemsgroup.com>
Subject: Re: [TowerTalk] Tower Base Concrete Cure Time
From: jimlux <jimlux@earthlink.net>
Date: Fri, 07 May 2010 12:07:15 -0700
List-post: <towertalk@contesting.com">mailto:towertalk@contesting.com>
Jim Brown wrote:
> On Fri, 7 May 2010 12:53:49 -0400, Mark Robinson wrote:
> 
>> I poured the base for my Rohn 45 this morning. This tower is held upright 
>> with a wall bracket at 18 feet. How long should I leave the concrete to cure 
>> before starting work to add the next sections?
> 
> Concrete cures as a "sort of" inverse exponential function over time. One 
> month is the generally accepted time to wait. 
> 
> 

There are a variety of concrete handbooks out there (go to cement.org, 
for instance).. 28 days is when the concrete will have reached its "data 
sheet" spec.  It still keeps getting stronger for years. You're about 
50% of the 28 day strength in 7 days. You MUST keep the surface wet for 
the entire cure time.

If you let the surface dry out, it actually cures to 50% strength 
faster, but will never get to the 28 day strength. There's an 
interesting chart I found some years ago that shows if you air cure, the 
max strength after months is about 50%.  If you keep it under water for 
3 days, then let it dry, it will get to 80%, 7 days of under water gets 
it to 90%


So, if you're pouring a slab for a patio, you may not worry if you just 
keep it wet for a few days.. But the footings for your house or your 
tower?  Here in southern California, a popular strategy is to use 
plastic film over the concrete to keep it wet (along with the water 
under the film, of course).  There's also various chemicals (some as 
simple as diesel fuel) they spray on which reduce some of the evaporation.

It sort of depends on what you want to do.  Will it hold up to the full 
design loads in a week?  Probably not.  Is it strong enough to erect the 
rest of the tower, if the weather is going to be good and you're not 
going to see the rated, probably..  It's a gamble.. do you feel lucky?


If you want more information on this than any ham needs to know, here's 
the Federal Highway Administration's
"Guide for curing of portland cement pavements"
http://www.fhwa.dot.gov/pavement/pccp/pubs/02099/index.cfm

It has charts and graphs, and equations to model the evaporation of the 
water coming out, factoring in temperature and wind, and how to maintain 
the optimum hydration profile..  Hey, if you're building a freeway at 
millions of dollars/mile, you want that concrete to be as good as it 
gets..Memorize this puppy, and when you're at Dayton in a couple weeks, 
and folks start spouting various theories of concrete use, you can just 
stop them in seconds.. You can talk about water reducing admixtures, 
bleed rates, etc.


By the way, the above document talks a bit about how cement chemistry 
has changed over the last few decades. On big construction projects, 
waiting time is big money, so there's a lot of interest in not just 
saying "it's cured after 28 days".  So, they want to predict (and 
measure) the strength accounting for temperature, hydration, etc.
_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>