Tom,

Base was poured in August 2012. I actually wrapped a blanket around the base 
and kept that damp. This was recommended by the concrete vendor.

It has been in for over a year and already gone through one New Hampshire 
winter with no issues.

Doug - K1ZO

  ----- Original Message ----- 
  From: Tom Anderson 
  To: Larry Loen ; Doug Scribner 
  Cc: Towertalk 
  Sent: Friday, November 01, 2013 3:20 PM
  Subject: Re: [TowerTalk] concrete


  Doug:

  One thing you might do is what I was told when I put in my base back in 1993. 
 Lightly water the concrete base daily.  I mean lightly, no gushers,  etc. Just 
a sprinkle for a couple minutes.  This helps take out the heat from the curing 
concrete.   I mnust have worked because my 4x4x6 ft base is still in fine shape 
as when I put it in.

  Tom, WW5L




    From: Larry Loen <lwloen@gmail.com>
    To: Doug Scribner <dscribner@myfairpoint.net> 
    Cc: Towertalk <towertalk@contesting.com> 
    Sent: Friday, November 1, 2013 2:10 PM
    Subject: Re: [TowerTalk] concrete


    My US Tower first advised 90 days, but the eventually relented and told me
    28.  I think I waited six to eight weeks; don't remember now.

    Remember, though, that none of us are structural engineers. You might want
    to check around to be sure.  But, I believe that's standard information and
    you should be able to google something up from a reputable source.



    WO7R


    On Fri, Nov 1, 2013 at 12:02 PM, Doug Scribner 
<dscribner@myfairpoint.net>wrote:

    > When I poured my base I was told to wait 28 days, at which time the
    > concrete should reach 90% of its strength.
    >
    > Doug - K1ZO
    >
    > ----- Original Message ----- From: "Rex Turvin" <turvin2009@yahoo.com>
    > To: "towertalk" <towertalk@contesting.com>
    > Sent: Friday, November 01, 2013 2:49 PM
    > Subject: [TowerTalk] concrete
    >
    >
    >  I'm going to be pouring concrete for my base foundation and 3 guy anchors
    >> next week. Does anyone know how long I need to let it cure beforeI start
    >> erecting the tower?
    >> 73 NR6M
    >>
    >>
    >> ex: KF7NMD
    >>
    >>
    >> Sincerely,
    >>
    >>
    >> Rex Turvin
    >> http://www.nr6m.com/
    >> ______________________________**_________________
    >>
    >>
    >>
    >> ______________________________**_________________
    >> TowerTalk mailing list
    >> TowerTalk@contesting.com
    >> 
http://lists.contesting.com/**mailman/listinfo/towertalk<http://lists.contesting.com/mailman/listinfo/towertalk>
    >>
    >>
    >>
    >> -----
    >> No virus found in this message.
    >> Checked by AVG - http://www.avg.com/
    >> Version: 2013.0.3426 / Virus Database: 3222/6799 - Release Date: 11/01/13
    >>
    >>
    > ______________________________**_________________
    >
    >
    >
    > ______________________________**_________________
    > TowerTalk mailing list
    > TowerTalk@contesting.com
    > 
http://lists.contesting.com/**mailman/listinfo/towertalk<http://lists.contesting.com/mailman/listinfo/towertalk>
    >
    _______________________________________________



    _______________________________________________
    TowerTalk mailing list
    TowerTalk@contesting.com
    http://lists.contesting.com/mailman/listinfo/towertalk



  No virus found in this message.
  Checked by AVG - www.avg.com
  Version: 2013.0.3426 / Virus Database: 3222/6799 - Release Date: 11/01/13
_______________________________________________



_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk

<Prev in Thread] Current Thread [Next in Thread>