wot i do is pass a nother cable from the bottom of the tower section
being lifted out the top for the hook to lift on when all is in
position u only need to go to the 20 ft lrvel to un hook the lift
cable u put in side ur tower section.. when doing a new tower from gnd
up in my case 100ft towers i do not need to climb the tower at all
just disconnect at gnd level..
Quoting John Harper <john@ae5x.com>:
> Please pardon the dumb question...I'm on new turf:
>
> In a couple weeks, a crane will be coming to raise 30 feet of Rohn
> 25 tower (in one piece) onto the existing 20 feet already in the
> ground. How does the crane normally release from the section to
> which it's attached? That point will now be 50 feet high and I know
> taller towers are raised this way.
>
> Is the tower attached to the crane by the hook, which falls away
> once there is no longer a load on it or is there some other way
> (short of climbing up there to untie)?
>
> Tnx/73,
>
> John AE5X
> The tower in progress:
> http://www.ae5x.com/blog/tower-installation/
>
> _______________________________________________
>
>
>
> _______________________________________________
> TowerTalk mailing list
> TowerTalk@contesting.com
> http://lists.contesting.com/mailman/listinfo/towertalk
>
_______________________________________________