I am planning the installation of a self-supporting tower. My contractor
asked me a question to which I don't know the answer. Is there any reason
why he cannot pour the base in two pours as long as they are tied together
by the rebar cage? The plans call for the foundation to be 9 x 9 at the
base and then 5 x 5 at the surface. He would prefer to pour the 18" thick
9 x 9 foot section before the 5 x 5 foot section. Any reason why not?
Thanks
Wes, WZ7I