Bob Kellow, W5LT W5LT at comcast.net
Mon Oct 24 12:01:45 EDT 2005


James:
Several ways:
See the following for how Heights suggests doing it for an embedded base:
http://www.heightstowers.com/bases.htm

Also, I designed the fold-over bases for them, which uses standard threaded
anchor bolts (valmont) inconjunction with a "U" shaped weldment, which can
be seen at:

http://www.heightstowers.com/fold_over_kits.htm

The tower legs can be adjusted AFTER the pour to make everything plumb, very
flexible.

73's

Bob, W5LT 

-----Original Message-----
From: James E. Lanier [mailto:jelanier at chemroc.com] 
Sent: Monday, October 24, 2005 7:47 AM
To: towertalk
Subject: [TowerTalk] Plumbing Universal Tower

The base for the Universal Tower (7-40) is a one shot deal it appears. Any
ideas or solutions to leveling after the fact?

I have not poured yet and I am hoping for the best, but I only have the
bottom section to plumb. Adding sections tends to multiply errors.

I wonder if anyone here has created an adjustable base plate mount for this
type of tower. 