On 5/16/2018 3:55 PM, Mike NA6MB wrote:
There is a good QST article here:

I would change the word "good" to "flawed." The best things about it are that 1) it emphasizes the importance of twisted pair and shielding for all wiring carrying noisy current; 2) that the system as installed (and pair for) was VERY noisy by virtue of bad design of its components and by the installation; and 3) it takes a LOT of work (and money) to fix a bad system.

73, Jim K9YC