Gary McConville wrote: > Roger, > Unless the math has changed, it looks like you'll need > 72 sq ft or 8 cubic yards. Geez, I certainly hope not. Actually, the total square feet of a 4X4X5' hole is 80 cubic feet. But a cubic yard has 27 cubic feet of concrete in it. And 80/27=2.96 cubic yards. If you can't pay for a pumper, then you're left with 2 choices. Dig another hole, or cart it back there and do it the hard way. ):> Ed |