I am looking for someone with experienced who have used a crane for tower
installation of 45g. I plan on hiring out the service but I am not sure if
the best thing to do is to have the tower in 1 or multiple sections for the
install. Also was considering have the rotor, mast and 2m/440 vertical
mounted before the lift. Can the 45g handle the weight without buckling
? Right now the plan is to put up the 10 sections all at once (guyed).
Please advise.
~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~
DO NOT do 10 sections of 45 all at once. It is a disaster in the making. I
have done nine sections of 55 all at once and would be comfortable doing
it....but not nine sections of 45, especially with all that stuff on it.
Bill KH7XS/K4XS
************************************** Get a sneak peek of the all-new AOL at
http://discover.aol.com/memed/aolcom30tour
_______________________________________________
_______________________________________________
TowerTalk mailing list
TowerTalk@contesting.com
http://lists.contesting.com/mailman/listinfo/towertalk
|