Topband: Top Loading of Shunt-fed Tower
Joe Subich, K4IK
k4ik at subich.com
Thu Feb 10 23:44:18 EST 2005
Tom,
> He said be sure to ground the control cable and choke
> everything off, as a fried control unit is the problem
> he would be most concerned about.
SteppIR uses a shielded control cable. If your tower is
grounded at the base (shunt fed) and you bring the cable
completely to the bottom of the tower, the only real
concern would be to tie the shield of the control cable
to the tower ground.
Good practice world also call for the shield to be tied
to the common entry point ground (where all coax shields
are grounded before entering the building). With two
"ground" points there should be no problem. However,
if you want to take a belt and suspenders approach.
wind the control cable on some 2" to 3" PVC pipe making
a solenoid 18" or so long and put it just after the
tower ground and before the control cable goes into
the conduit to the house ... that's what I'll be doing
with mine.
73,
... Joe, K4IK
More information about the Topband
mailing list