Re: [TowerTalk] Legs of a 60' piece of tower being dragged while being l

To: "Jeff Draughn" <n0ost99@gmail.com>
Subject: Re: [TowerTalk] Legs of a 60' piece of tower being dragged while being lifted
From: "StellarCAT" <rxdesign@ssvecnet.com>
Date: Fri, 14 Oct 2016 09:10:51 -0400
List-post: <towertalk@contesting.com">mailto:towertalk@contesting.com>
Indeed you are correct ... however space is the limitation. The 60’ piece was 
assembled with the top nearest the crane and going away from that spot – that 
distance it goes away is probably too far for the crane as it would need to 
boom out too much... with hindsight I might have tried to do it differently to 
accomplish this better but even thinking about that I don’t think it would have 
been possible with 6 antennas all assembled scattered around. The space where 
it would have had to go is where I had to stage the 50’ boom 5 el 20 in order 
to get it pre-assembled on to a 14’ tower section – it and the 80/75 dipole are 
at the top and I had to use that space to get it ready (its now done and ready 
to go). 

g.



From: Jeff Draughn 
Sent: Friday, October 14, 2016 9:05 AM
To: StellarCAT 
Cc: tower 
Subject: Re: [TowerTalk] Legs of a 60' piece of tower being dragged while being 
lifted


I may be all wet here, especially since I have never done this before, but it 
seems if you position the base of the section you want to lift near the tower 
you want to lift it onto then swing the boom of the crane to pick up the end, 
as you pick it up if you swing the boom back towards the base of the section 
you're lifting there would be very little dragging involved. 

Again without having real life experience at doing this I may be completely 
off-base but just a thought.

Jeff


On Friday, October 14, 2016, StellarCAT <rxdesign@ssvecnet.com> wrote:

  So Fred pointed this out ... I hadn’t considered it up until then... is it a 
problem to just allow the legs drag in the dirt while the 60’ piece with 
rotating ring attached (~850#) is lifted? Is there ANY chance the legs will 
deform making it impossible to mate it to the tower? I don’t have access to an 
end loader or any other piece of heavy eqmt ... I thought, and this might sound 
silly, a dolly ... those cheap(er) ones – seem to be rated at 600# ... if I 
could get enough guys to lift the end and put that under the end – then we 
could pull it along as the crane goes up.... although the ground is really 
rough so that is doubtful... it would probably get stuck and the legs drop off 
which would be far worse than just having them drag on the ground ... 
experiences anyone?

  Gary
  _______________________________________________



  _______________________________________________
  TowerTalk mailing list
  TowerTalk@contesting.com
  http://lists.contesting.com/mailman/listinfo/towertalk
_______________________________________________



_______________________________________________